A Later Start This Sunday
Line 1 will open a little later than usual this Sunday, Nov. 15, with service beginning at noon instead of the regular morning start. The delay is to allow crews to install a fix for train software issues that general manager Rick Leary confirmed has now been resolved.
Riders won’t be left stranded in the meantime. The usual weekend replacement plan will be in effect that morning, with R1 buses running between most rail stations and shuttle buses covering the rest.
Test Trains Head for Trim
The bigger milestone lands on Sunday, Nov. 22, when every Line 1 train is scheduled to begin running past the line’s current end point and all the way out to the extension’s five new stations, finishing at Trim. Passengers will still need to disembark at Blair, where the open portion of the line currently ends, and OC Transpo staff will be on hand there to help everyone off.
According to Leary, this will mark the first time Rideau Transit Maintenance puts all 23 trains into service at once, running roughly every four and a half minutes. It’s a key dress rehearsal for vehicles, schedules and staffing before the line moves into its next testing phase.
What Comes After Pre-Trial Running
Those November test runs are what’s known as the lead-up to Pre-Trial Running, expected to last about a week if all goes smoothly. From there, the extension would move into 21 days of formal trial running, where trains are put through their paces against performance, safety and reliability benchmarks.
Even after trial running wraps up, there’s still five to 10 days of prep work and final certification ahead before the public can actually board. All told, that puts the earliest realistic public launch at around five weeks after pre-trial running begins.
Where You’ll Be Heading
Once open, the extension will run largely alongside Highway 174, connecting riders to five new stations: one near the Montreal Road interchange, another at Jeanne d’Arc, a stop by the Orléans Boulevard overpass, one serving Place d’Orléans mall, and the final stop at the Trim Road park-and-ride.
For east end commuters who’ve spent years eyeing those unused platforms, it’s a sign that an easier ride into downtown is finally within reach. Keep an eye on OC Transpo’s updates as testing unfolds this fall.